The CAPEX estimation tool is designed to help you estimate your projects CAPEX which is needed to run the Techno-economic analysis tool. Below, you can input the parameters of your project to see the resulting project cost in both hard and soft costs.
The CAPEX tool operates on the following Foundational assumptions:
This category represents the cost of solar PV modules for the project.
This category includes all installation costs associated with the FPV installation. This includes installation for all components across the previous segments, and construction of support structures such as concrete equipment pads.
This category includes the estimated cost of substation upgrade based on project size and interconnection voltage.
The cost of all racking components and racking structures, including floats, panel mounts, and associated racking hardware. This category does not include additional materials outside of the floating structure, such as anchor and mooring materials, wiring, or electrical equipment.
This category includes all electrical balance of system wiring costs associated with the DC electrical components of the FPV. Specifically, this includes wiring along rows to combiner boxes and combiner boxes to inverters.
This category includes all material associated with anchors, mooring lines, and related materials. This category does not include installation cost for anchor/mooring, or the associated machinery needed for anchor deployment (e.g., barges, divers).
This category represents the cost of inverters for the project.
This category includes all electrical balance of system components on the AC portion of the FPV installation. Specifically, this includes wiring from inverter to transformer.
The gen-tie category includes all wiring/tie-in equipment from the transformer to substation. This also includes overhead and underground MV conductors.
This includes EPC profit for all activities and overhead costs such as lodging, bonding, warranties, and insurance.
This category includes additional equipment such as SCADA systems, weather stations, and underground trenching for fiber communications cables and commissioning activities such as performance testing.
This category includes larger construction-related expenses such as rental construction equipment, civil work, security system, and temporary ramp construction.
This includes engineering fees, permits, and engineering surveys.